Key events and scheduled submissions in the Twiggs County BESS proceeding include:
- August 9, 2024: Georgia Power issued the Winter 2027-2028 BESS RFP seeking approximately 500 MW of capacity, with in-service dates on or before November 30, 2027
1.
- August 23, 2024: Georgia Power filed revised RFP documents. Commission approval (with modification) occurred on September 24, 2024
2.
- September 13, 2024: Deadline for company-owned BESS RFP proposal submissions. For other bids, the deadline was September 16, 2024
2.
- November 7, 2024: Deadline for remaining bidders to post bid security
2.
- December 28, 2024: One bid was released due to a commercial operation date issue
2.
- April 24, 2025: Anticipated extension deadline for finalizing RFP evaluations and shortlist
2.
- May 14, 2025: Georgia Power completed evaluation of competitive tier bids and selected the Twiggs County BESS project for certification
2.
- May 22, 2025: Reserve list proposals were released due to inability to achieve the required commercial operation date
2.
- June 20, 2025: Georgia Power filed its application for certification of the Twiggs County BESS project with the Commission
1,
3.
- June 26, 2025: Certification fee of $101,003.49 to be paid by Georgia Power for the Commission’s review of its certificate filing
4.
- July 15, 2025 (no later than): Georgia Power to give first notice of its proceedings in this case
4.
- 30 days after first notice: Deadline for parties to file applications to intervene in the proceeding
4.
The proceeding will also include a hearing and potential subsequent steps as ordered by the Commission
3.