Key events and submissions in the Goldfinch Solar proceeding (Iowa Utilities Board Docket No. GCU-2022-0002) include:
- July 15, 2022: Goldfinch Solar filed a request with the Iowa Utilities Board (IUB) for a public informational meeting in preparation for seeking a generating certificate for a 200 MW solar project in Washington County, Iowa
1,
1.
- September 26, 2022: The required public informational meeting was held in Ainsworth, Iowa
1,
1,
2.
- May 2, 2023: Goldfinch Solar filed its application for a Certificate of Public Convenience, Use and Necessity (CPCN) with the IUB
1,
1,
1.
- May 17 and June 20, 2023: Goldfinch Solar submitted additional information to complete its application
1,
1,
1.
- July 25, 2023: Goldfinch Solar requested waivers of certain hearing requirements under Iowa Code §§ 476a.4 and 476a.5 and specific administrative rules
1,
1,
1.
- August 4, 2023: The IUB issued an order accepting the application as substantially complete and set a limited procedural schedule, with intervention requests, objections, and comments due within 30 days
3,
3.
- September 1, 2023: Great Plains Laborers’ District Council filed a petition to intervene
1,
1.
- September 5, 2023: Deadline for intervention requests, objections, and comments
1,
1.
- September 12, 2023: Goldfinch Solar filed a response supporting the waiver of a hearing and confirming notice to landowners
4.
- November 16, 2023: The IUB issued an order granting waivers, intervention, confidential treatment, and the application for a certificate of public convenience, use and necessity
1.
- Construction anticipated to commence in April 2024, with commercial operation projected for October 2025
1,
3.
Additional requirements include Goldfinch Solar filing status updates on permit acquisition, notice of construction commencement within 10 days, and progress updates at 50% and final completion. Decommissioning notification is required at the end of project operation
1.