Key events and submissions in the Otter Tail Power Company (OTPCO) proceeding for approval of an electric service agreement (ESA) with Big Stone South Energy Storage Project, LLC (BSSEP) and associated tariff revisions are as follows:
- April 21, 2025: Otter Tail Power Company filed its petition and associated confidential materials with the South Dakota Public Utilities Commission (SDPUC) seeking approval of an ESA with deviations for BSSEP and associated tariff changes
1,
2.
- April 22, 2025: The filing was officially received by the Commission. Notices of the filing and intervention deadline were electronically transmitted to interested individuals and entities on the Commission's listserv on April 24, 2025
3,
3.
- May 9, 2025: Deadline for intervention or comments. No petitions to intervene or comments were filed
3,
3.
- May 14, 2025: SDPUC staff served the first set of data requests on the parties
2,
2.
- May 28-29, 2025: Otter Tail responded to staff data requests
3,
4.
- June 16, 2025: Staff served a second set of data requests on the parties
5.
- June 17, 2025: Otter Tail responded to data requests
3,
3.
- July 15, 2025: The Commission considered the matter at its regular meeting and voted unanimously to approve the ESA with deviations and associated tariff revisions
3,
3,
3.
- July 17, 2025: The Commission issued its order granting approval of the ESA with deviations and approving tariff revisions, effective August 1, 2025
3,
6,
3,
3,
3.
- July 23, 2025: Otter Tail filed a compliance filing with the final version of tariff section 16.00 reflecting commission-approved changes
7,
7.
- August 1, 2025: Effective date for the new electric service agreement and revised tariff sheets
6,
8,
8,
8,
1,
1.
Throughout the process, confidential treatment was requested for proprietary and sensitive information included in the filings
9,
9.