Key events and submissions in the Washington Gas leak inquiry proceeding (Case No. 9035) as documented in the excerpts:
- April 7, 2005: The Maryland Public Service Commission issued a Notice of Inquiry that initiated ongoing reporting requirements for Washington Gas regarding natural gas leaks
1.
- April 12, 2006: Modification to the original reporting requirements, adjusting the reporting protocol for the proceeding
1.
- August 8, 2006: Washington Gas modified its rehabilitation project to address mechanical coupling leaks in Prince George's County
1,
2.
- Fall 2015: Washington Gas, Staff, and the Office of People’s Counsel met to review submitted leak data, including hexane injections, and agreed on an annual meeting regarding the hexane injection program going forward
1,
2.
- January 15, 2021: Filing of the 59th quarterly report, including data analysis and z-value calculations for monthly leaks
3.
- April 14, 2021: Filing of the 60th quarterly report, with updates on leak surveys, repairs, and completed rehabilitation project
1.
- October 15, 2021: Filing of the 62nd quarterly report, confirming completion of the rehabilitation project and ongoing monitoring/replacement efforts
2.
- October 17, 2022: Filing of the 66th quarterly report
4.
- July 17, 2023: Filing of the 69th quarterly report
5,
6.
- January 15, 2025: Filing of the 75th quarterly report, including updated annual leak data for Montgomery and Prince George's Counties through 2024
7.
- April 15, 2025: Contact and service list update for counsel and representatives in the proceeding
8.
- April 21, 2025: Official appearance and representation change for the Maryland Office of People’s Counsel in this case
9.
Washington Gas has continued to submit quarterly reports as required, with key milestones marked by changes to reporting protocol, completion of rehabilitation projects, annual meetings for specific technical reviews, and periodic updates to stakeholder contact information.