Key events and submissions in the Emerson Creek Wind Farm proceeding (Case No. 25-0495-EL-BGA and related cases):
- January 31, 2019: Initial application for a certificate of environmental compatibility and public need filed with the Ohio Power Siting Board (OPSB), with supplements on March 18, April 11, July 10, and September 12, 2019 (Case No. 18-1607-EL-BGN).
- September 11, 2020: Joint stipulation and recommendation filed by the applicant, OPSB staff, Huron County, City of Willard, Norwich and Richmond Townships, and local residents.
- June 24, 2021: OPSB issues certificate authorizing construction and operation of the wind facility (up to 297.66 MW).
- October 29, 2021: Application for first amendment filed (Case No. 21-1055-EL-BGA), with supplements on March 20 and July 26, 2023. Addresses turbine location shifts, updated geotechnical info, slight project area expansion, and minor design modifications.
- August 25, 2023: OPSB staff report issued for first amendment.
- November 16, 2023: OPSB issues order approving first amendment.
- August 30, 2024: Second amendment application filed (Case No. 24-845-EL-BGA), addressing turbine shifts, addition of access road, further design shifts, and landowner feedback.
- November 11, 2024: OPSB staff report issued for second amendment.
- January 16, 2025: OPSB issues order approving second amendment.
- April 28, 2025: Third amendment application filed (Case No. 25-0495-EL-BGA).
- May 7, 2025: Inspection date for the third amendment.
- April 16–17, 2025: Field delineation work for wetlands and streams conducted.
- May 5, 2025: Anticipated submission date for final wetland and stream delineation report to OPSB.
- Early May 2025: Anticipated completion of Phase I archaeological fieldwork for modified facilities.
- May 29, 2025: Applicant responds to second OPSB staff data request, clarifies wetland count.
- June 2, 2025: Staff report issued and filed for third amendment; report date for latest staff investigation.
This timeline covers the major filings, amendments, investigations, and scheduled studies in the project’s regulatory review process through mid-2025