Key events and submissions in this proceeding include:
- July 24, 2020: Board meeting held; quarterly report for period ending June 30, 2020, filed with the commission on July 31, 2020
1.
- October 26, 2020: The commission filed an information request regarding a transfer of $34,004,860.68 by HGIA
2.
- October 28, 2020: Board meeting held
2.
- January 30, 2023: Board meeting held; approved secretary’s certificate for USDA RESP loan and HGIA’s quarterly report for period ended December 31, 2022
3,
4.
- January 31, 2023: Quarterly report for period ended December 31, 2022 filed with the commission in docket no. 2014-0135
3,
4.
- March 10 & 20, 2023: Public comments filed supporting HGIA’s request to finance community solar projects
3,
5.
- March 31, 2023: Board meeting held; HGIA’s FY2024 annual plan approved and filed with the commission
3.
- August 12, 2022: Program Notification No. 15 filed, requesting seven changes to the GEMS program
6,
6.
- August 30–31, 2022: Commission established procedural schedule to review Program Notification No. 15; public comment filed in support
7,
6,
6.
- June 16, 2023: Order No. 39377 filed, approving in part, denying in part, and modifying in part the requests under Program Notification No. 15
5.
- September 25, 2023: $3,716,042 transferred to PUC account at Bank of Hawaii
5,
8.
- December 28, 2023: HGIA distributed its 2023 annual report to the governor and legislature
5.
- January 29–30, 2024: Board meeting held; quarterly report for period ended December 31, 2023 filed
5.
- April 30, 2024: Next quarterly report scheduled to be submitted covering activities from January 1 to March 31, 2024
5.
This timeline highlights regular quarterly and annual reporting, program modification submissions (notably PN15), related board meetings, and significant financial transactions throughout the proceeding.