Key events and submissions in this proceeding include:
- March 17, 2025: The application materials reference a date of preparation and submission for project documentation by Switch, Ltd.
1.
- May 1, 2025: Switch, Ltd. filed an application with the Public Utilities Commission of Nevada (PUCN) for a Utility Environmental Protection Act (UEPA) permit to construct four 345 kV transmission lines and associated facilities in Storey County, Nevada. This filing initiated Docket No. 25-05001
2,
2.
- May 5, 2025: The Commission signed the official notice of the application
2,
2.
- May 9, 2025: Public notice of the application was published in the Comstock Chronicle, fulfilling statutory notification requirements
2,
2.
- May 21, 2025: A public hearing regarding Storey County School District’s tentative budget is scheduled (related notice published on the same timeline, indicating coordinated public notifications but not directly part of the UEPA proceeding)
2,
2.
- May 28, 2025: Deadline for interested parties to file comments on the Commission’s website regarding the project
2,
2.
- September 2025: Anticipated start of construction for the major transmission line segment (Comstock line), with a projected in-service date of April 2026
3.
Additional procedural notes:
- The application and supporting documents are available for public review on the PUCN website and at Commission offices.
- Interested parties may file for intervention or submit comments by the stated deadlines to participate in the proceeding
2,
2.
This timeline summarizes the major filings and scheduled events as documented in the proceeding.